Castleforge , Clockwise

Ardmac completed the Fit out of Edward Pavilion in Liverpool, on behalf of Castleforge Partners, for serviced office provider Clockwise. The site now caters to businesses of all kinds, ranging from freelancers to SMEs. It also regularly hosts Clockwise networking events and conferences.

Ardmac together with weare74 architects were required to Design & Build Cat A + B across 4 Floors of the Grade 1 Listed Building comprised of 3 floors of offices, reception, basement showers & changing, toilets to all floors and refurbishment of the two passenger lifts. Additionally, we completely changed all building services (electrical & mechanical). A BREEAM Very Good standard was required. the client team comprised Linesight, Malcolm Hollis, Aedas and LSD.

Client: Castleforge

Location: Liverpool

Size: 70,000 sqft

Duration: 21 weeks