Modular Testing Facility
Modular testing facility comprised of six external modules
Client: Confidential
Location: Oxfordshire, England
Project Size: 184m2
Duration: 40 Days
This project involved the creation of a modular testing facility made up of six external modules. The client needed a rental option that could be quickly deployed. These units were installed on an existing site, adjacent to a current facility, and were designed to operate independently, complete with HVAC and electrical utilities. The entire project was delivered in just 76 days, with Ardmac completing the Off-Site Manufacturing (OSM) process, from site setup to handover, in just 40 days.
Meeting The Client’s Requirements
The client required a cutting-edge modular testing facility to be delivered within a strict timeline. The project presented various challenges that needed to be resolved without affecting the overall schedule.
The facility was to consist of six external, fully self-sufficient modules, complete with integrated HVAC and electrical utilities. Midway through the project, additional requirements were introduced, including extra electrical sockets and modifications to the mechanical and electrical (M&E) scope, such as installing a chiller and compressor. These changes necessitated additional cabling, procurement, and man-hours, creating potential risks to the project timeline.
The electrical work duration increased from 5 days to 11 due to the extensive cabling required. However, a mitigation plan was implemented to recover lost time by overlapping tasks with the testing and commissioning phases, ensuring the project remained on track.
The Solution
Ardmac, a leading international construction specialist recognised for delivering high-quality and innovative solutions, was chosen for the project. Ardmac’s expertise in off-site construction made them an ideal partner for this fast-paced initiative.
By leveraging lean tools and efficient reporting, Ardmac maintained seamless project management, providing the client with a sense of confidence and control. This structured approach was key to ensuring the project’s successful delivery. Ardmac’s careful planning and precise execution enabled them to effectively address the additional requirements without compromising the timeline or quality.
The Results
Ardmac successfully delivered the project within the planned 76-day timeframe, completing the Off-Site Manufacturing (OSM) phase, from site setup to handover, in just 40 days. Through strategic mitigation plans and task overlapping, the team minimised delays and ensured the project stayed on schedule.
The facility, composed of six modules, included a 106 m² testing area and a total facility size of 184 m². This achievement highlights Ardmac’s expertise in managing complex projects efficiently while upholding exceptional construction standards.
Our clients work at the forefront of innovation. Our innovative cleanroom solutions are built on trust, collaboration and technical expertise. We never compromise on safety.